Armanis Concentrator

Construction progress Commencement of construction – May 2008.
Completion of construction works – July 2011.
Site Development Concentrator - 10 ha.
Mine maintenance complex - 2,6 hа.
Open pit - 17 hа.
The Size of Construction Site development about 27,263 square meters (buildings and constructions of production, maintenance and administrative facilities).
Road: Stepanavan (City Centre) – Armanis region, 7.5 km.
Water supply with water intake – 8.8 km.
110/35/6 kW high-voltage el. line, 3.5 km.

The Concentrator will be processing polymetallic ore by flotation method, with the extraction of base metals (gold, copper, lead, zinc) producing 3 types of concentrates totaling about 34-37 thousand tons per annum.

Laboratories are equipped mainly with equipment of German manufacturers Kottermann and Carl Roth. The Concentrator will be equipped with the newest equipment manufactured mainly by German and Chinese producers.